Scheduled Power Interruptions in Multiple Sectors Due to ETED Maintenance
The Dominican Electric Transmission Company (ETED) will conduct maintenance on August 29, impacting multiple sectors. This work is crucial for the reliability of the electrical grid and involves replacing structures on a key transmission line.

On August 29, from 8:00 a.m. to 2:00 p.m., ETED will perform maintenance on the 69 kV Haina-Herrera Nueva-Metropolitano L3 transmission line, leading to power interruptions in sectors including El Millón, Los Prados, and Bella Vista. Additional affected entities include Claro Dominicana, Banco Popular, and Plaza de la Salud.
This operation is essential for maintaining infrastructure integrity and enhancing service reliability. The work reflects ETED's ongoing commitment to strengthening the electricity transmission network, which is vital for the Dominican Republic's energy transition.




Comments