Brenmiller Energy Completes Electrical Works for Tempo Project, Commissioning Set for February 2026
Brenmiller Energy Ltd. reports completion of electrical works at the Tempo project for Tempo Beverages Ltd., enabling full electrification of the thermal energy storage system. Commissioning activities are expected to begin in mid-February 2026. The project aims to replace 100% of the site's natural gas boiler-based heat production with a 32 MWh TES installation, eliminating 6,200 tons of CO annually.

Brenmiller Energy Ltd. has completed electrical works for its Tempo project, a thermal energy storage solution for Tempo Beverages Ltd. This milestone enables full electrification of the TES system, which is now capable of large-scale electric charging.
Commissioning activities are scheduled to commence in mid-February 2026. The project includes a 32 MWh TES installation designed to completely replace natural gas boiler heat production, eliminating 6,200 tons of CO annually. This initiative is a pivotal step in Brenmiller's transition from technology development to commercial deployment.




Comments