CyrusOne and Eolian Collaborate on 200 MW Data Center Campus in Fort Worth, Texas
CyrusOne and Eolian have partnered to develop the DFW7 data center campus in Fort Worth, Texas, which will feature 200 MW of capacity supported by existing high-voltage infrastructure. Construction commenced in April 2025, with operations slated to begin in 2026, while Eolian will enhance a battery energy storage system at the Chisholm Grid site to improve energy supply and grid reliability in North Texas. This collaboration is designed to facilitate hyperscale growth in the region.

CyrusOne and Eolian announced a partnership for the DFW7 data center campus in Fort Worth, Texas, leveraging existing high-voltage infrastructure to deploy 200 MW of capacity. Construction began in April 2025, with operations expected to start in 2026.
Eolian will modernize a battery energy storage system at the Chisholm Grid site, enhancing energy supply for the data center. This collaboration aims to support hyperscale growth and improve grid reliability in North Texas.