East Vincent Planning Commission Recommends Denial of Pennhurst Data Center Project

POWER GRIDS & TRANSMISSIONDATA AND AI INFRASTRUCTURE

The East Vincent planning commission unanimously recommended that the township's board of supervisors deny a data center project at the historic Pennhurst site due to technical deficiencies and non-compliance with zoning ordinances. Residents have opposed the plan, which involves five two-story buildings, an electrical substation, and a solar field totaling over 1.3 million square feet.

The developer intends to revise the proposal but did not attend the commission meeting, which drew criticism. A conditional use hearing is set for March 16, and if an updated plan is submitted, it may return to the commission.

East Vincent Planning Commission Recommends Denial of Pennhurst Data Center Project
Feb 19, 2026, 11:44 PM