Ethical Power Completes Sizing John Energy Storage Project Near Liverpool
ENERGY STORAGE
Ethical Power has completed the Sizing John Energy Storage Project, a strategic grid-balancing facility located near Liverpool. The project enhances Ethical Power's reputation as a reliable partner in high-voltage and storage solutions.
Ethical Power was appointed by asset owners Varco as the principal contractor, delivering a full turnkey solution that included design, civil works, and electrical connections at 33kV/132kV. Key components of the project involved a 600-metre off-site route connecting the client's substation to the National Grid's network and the procurement and commissioning of a 132kV substation with an auxiliary transformer on site.

Jan 9, 2026, 4:23 PM