Galaxy Digital Secures 830 MW Approval for Helios Data Center in Texas
DATA AND AI INFRASTRUCTURE
Galaxy Digital Inc. received approval from ERCOT for an additional 830 MW at its Helios data center in West Texas, doubling its total capacity to over 1.6 GW. The approval follows a Large Load Interconnection Study and a service agreement with AEP Texas Inc.
Construction is underway for the first phase, with initial power delivery expected in early 2026. Galaxy is exploring further power and land opportunities in Texas and other locations.

Jan 16, 2026, 6:06 PM