IMFA Kalinganagar Plant Achieves 220 kV Power Connectivity
The IMFA Kalinganagar facility has successfully established a 220 kV power connection from the New Duburi grid, enhancing its energy infrastructure. This milestone, completed by M/s AK Das Associates Limited, is vital for operational efficiency in the region's industrial sector.

The IMFA Kalinganagar plant has secured a 220 kV power connection from OPTCL's New Duburi grid substation, marking a significant infrastructure development. The project was executed by M/s AK Das Associates Limited and included the construction of a 220 kV bay extension, EHV cable system, and an overhead transmission line, completed in eight months.
Challenges included right of way constraints and complex engineering tasks. Successful project execution is expected to improve energy reliability for industrial operations in the area, while the collaboration between IMFA and OPTCL highlights the importance of partnerships in infrastructure projects.