Jati Tinggi Group Berhad has secured a RM79.86 million contract from TNB for underground cabling at a data center in Pasir Gudang, Johor. The work, to be carried out by Jati Tinggi Holding Sdn Bhd, includes laying 275kV double-circuit cables and a 'Bulk Supply' connection. The project is expected to be completed within 270 days, commencing on a date to be announced, with a 365-day defect notification period.

Jati Tinggi Group Berhad has been awarded a RM79.86 million contract by TNB for underground cabling works to support a data center in Pasir Gudang, Johor. This project, undertaken by its subsidiary Jati Tinggi Holding Sdn Bhd, involves the installation of 275kV double-circuit underground cables and a 'Bulk Supply' connection. According to the Letter of Acceptance dated March 2, 2026, the work is to be completed within 270 days from a yet-to-be-determined start date, and includes a 365-day defect notification period for the high-voltage connection.