Lake Gwayi-Shangani Project Relocation and Progress Update
The Lake Gwayi-Shangani project in Zimbabwe is set to relocate 806 families at a cost of US$28 million, ensuring progress toward water impoundment. Completion of the dam wall is targeted for year-end, contingent on consistent funding of US$8 million monthly for ongoing construction.

The Lake Gwayi-Shangani project, crucial for water security and irrigation in Zimbabwe, is relocating 806 families from Binga District at a projected cost of US$28 million. The dam will cover 10,000 hectares and has a storage capacity of 634.27 million cubic meters.
Completion of the dam wall is anticipated by year-end, dependent on monthly funding of US$8 million. Construction progress reports indicate that the dam wall is 82% complete, with supporting pipeline infrastructure at 46% completion.
A mini-hydropower station, generating 10 megawatts, is also underway. Cultural considerations for the affected families remain a point of concern, necessitating consultations to respect traditional practices. Failure to successfully relocate families could delay water impoundment, impacting regional water security.




Comments