Milford Council Approves Water Treatment Project Change Order and Other Initiatives
The Milford Council approved a change order for the water treatment plant totaling $39,715 and extending the project timeline by 56 days. This order includes installing a new hydrant system, adding a sample tap, and replacing aging Variable Frequency Drivers (VFDs).

The Milford Council approved a change order for the water treatment plant amounting to $39,715, extending the project timeline by 56 days. Key components of this change order include the installation of a new hydrant system, the addition of a sample tap for easier testing, and the replacement of ten-year-old Variable Frequency Drivers.
The funding will come from the town's $150,000 contingency. Additionally, the council discussed data center regulations, trail litigation updates, and renewed the town’s general liability insurance with a 6% increase. The utility superintendent confirmed the completion of water tower cleaning and received approval for a vehicle purchase.