Rețele Electrice România Invests RON 1.4 Billion in 2025 for Network Modernization
In 2025, Rețele Electrice România invested approximately RON 1.4 billion in the modernization of its electricity distribution networks. This investment is crucial for enhancing service quality, safety, and capacity, aligning with the ongoing energy transition.

Rețele Electrice România allocated RON 1.4 billion in 2025 for infrastructure upgrades, with RON 1.2 billion earmarked for operational projects. Key improvements were made in Muntenia, Banat, and Dobrogea regions, including the modernization of substations and power lines.
For 2026, the company plans to invest RON 1.3 billion, with RON 821.3 million from internal funds, targeting enhanced reliability and digitization of the network. European funding is also set to support projects valued at RON 1.36 billion from 2026-2029. The continued investments are expected to improve supply reliability and reduce operational costs, although dependency on external funding may present risks to project timelines.