St Chads Court Project Progress Update in Birmingham
The St Chads Court project in Birmingham is nearing completion with 233 student beds being prepared for the September intake. Major milestones include snagging over 120 apartments and completing furniture installation in four buildings.

The St Chads Court project is set to provide 233 student accommodation beds for Cassidy Group UK, with preparations for the September intake underway. In the last month, more than 120 apartments have been snagged, indicating substantial progress.
The substation is now operational, providing power across all buildings, and four of five blocks have completed furniture installation. Focus is currently on Block E, a historic building, which has finished plastering and mist coating, with kitchens and furniture installations scheduled for this week. Hard landscaping has also begun as part of the external preparations for handover.