Completion of MIX Marszewo Project: Poland's First 100 MW Cable Pooling Solution

SOLAR ENERGY

The MIX Marszewo project in Poland, completed by GOLDBECK SOLAR Polska, integrates the Marszewo Wind Farm and the Postomino Photovoltaic Power Plant using cable pooling technology. This system has a grid connection capacity of 100 MW and is one of the first of its kind at the 110 kV level in Poland.

The photovoltaic plant has an installed capacity of 90 MW and includes a modern control system for optimizing energy output from both installations. Construction began in spring 2024 and was completed by mid-2025, with the project being energized and operational by December 2025. The successful implementation involved collaboration among various stakeholders, ensuring project delivery within budget and schedule.

Completion of MIX Marszewo Project: Poland's First 100 MW Cable Pooling Solution