Dutchman Solar Project Plans Natural Gas Plant Near Glenrock, Wyoming
The Dutchman Solar Project, a 500 MW initiative in Converse County, seeks to allocate 409 acres for a proposed natural gas plant, Deer Creek, expected to generate 255 MW. This shift has prompted a reevaluation by local authorities, with a public hearing set for September 2, amid concerns regarding water usage and the project's overall impact on solar output.

The Dutchman Solar Project is set to become Wyoming's second-largest solar facility at 500 megawatts, with plans to generate $157 million in property tax revenue. A portion of the site is proposed for a natural gas power plant, Deer Creek, which would produce 255 megawatts if approved.
The project has been delayed, with construction now expected to begin in Q3 2027 and completion aimed for 2029. Converse County officials have raised questions about the gas plant's water requirements and its impact on solar generation capacity. The project remains in preliminary planning stages, requiring further evaluations and approvals.