Great Wolf Lodge Project in Jackson, TN Faces Delay Due to Archaeological Survey Requirements
The Great Wolf Lodge development project in Jackson, Tennessee, may experience delays due to required amendments and an archaeological survey mandated by the Army Corps of Engineers. The survey will increase costs by approximately $31,000, on top of the existing $525,000 contract ceiling. The Jackson City Council is set to discuss these additional costs on March 3.

The Great Wolf Lodge project in Jackson, Tennessee, initiated in 2021, may face delays following a Facebook post by Mayor Scott Conger. Compliance with state codes requires amendments to certain contracts, necessitating Jackson City Council approval.
Additionally, an archaeological survey mandated by the Army Corps of Engineers will add approximately $31,000 to the existing contract of $525,000 for professional engineering services from Neel Schaffer. The city council will meet on March 3 to further discuss the implications of these additional costs.