Gujarat BESS Seeks SCOD Extension and Liquidated Damages Waiver
Gujarat BESS Private Limited is pursuing an extension of the Scheduled Commercial Operation Date and a waiver of liquidated damages for its 180 MW/360 MWh project in Gujarat. The company cites several delays due to force majeure events and issues involving GUVNL and GETCO as the basis for its request.

Gujarat BESS Private Limited has requested the Gujarat Electricity Regulatory Commission (GERC) for an extension to the Scheduled Commercial Operation Date (SCOD) and a waiver of liquidated damages for its 180 MW/360 MWh project at the Charal GIS Substation. The project was subject to delays attributed to land acquisition issues, construction interruptions, and disruptions in supply chains.
GUVNL granted a 57-day extension, modifying the SCOD to February 21, 2026, but did not accept the full 152-day delay claim. Following a Force Majeure Notice issued in February 2026, GUVNL rejected the request in March and issued a demand for liquidated damages in May.
The GERC will hear further responses from GUVNL and GETCO by August 6, 2026, with a follow-up hearing scheduled subsequently. The regulatory outcome may impact future project timelines and stakeholder accountability.




Comments