Intermountain Gas Company to Replace Natural Gas Pipelines in Southwest Boise
NATURAL GAS
Intermountain Gas Company will replace natural gas mains and services in Southwest Boise as part of its integrity management process. The project, expected to take four to five months, involves replacing about 19,790 feet of main and 324 services.
Work is scheduled to start between March 16 and 30, and will necessitate brief interruptions in gas service for customers, who will be contacted for scheduling by the company. Completion is contingent on weather and unforeseen delays.

Mar 14, 2026, 1:16 PM