7C Solarparken AG Nears Completion of Reuden Süd PV Park with 20 MWp Capacity
7C Solarparken AG's Reuden Süd solar park, with a capacity of 20 MWp, is nearing completion ahead of its grid connection. The installation of the internal grid is underway, with the main substation powered and transformer stations being energized. The internal grid is expected to be operational by early March, followed by inverter start-up. The project will benefit from a feed-in tariff of 87 EUR per MWh until mid-2043.

7C Solarparken AG is nearing completion of the Reuden Süd solar park, which has a capacity of approximately 20 MWp and is set for grid connection. The 28-kilometer medium-voltage cable was successfully powered last week, and the internal grid installation is in progress.
The main substation is operational, and transformer stations are being energized daily. The internal grid is expected to be energized by early March, with inverter start-up to follow. The project secures a feed-in tariff of 87 EUR per MWh until mid-2043.