ERC Approves Grid Connection for RE Resources' 69.90 MWac Solar Project in Pangasinan

POWER GRIDS & TRANSMISSION

The Energy Regulatory Commission (ERC) has approved RE Resources Inc.'s application to connect its San Manuel solar project, producing 69.90 MWac, to the electricity grid. This project includes a 75 MVA, 69-kV substation and a 7-kilometer double circuit transmission line, with a total cost of P325.48 million.

Construction commenced on January 27 and is about 90% complete. The ERC reiterated that all power generation companies must secure authorization for similar projects to ensure coordinated system planning and grid integrity.

ERC Approves Grid Connection for RE Resources' 69.90 MWac Solar Project in Pangasinan
Feb 9, 2026, 1:40 PM