Preparatory work for the Radoszyce GT-1 geothermal well has begun in Radoszyce, Poland. The well will reach a depth of 1360 meters, targeting the Lower Triassic aquifer with expected temperatures of 40-45°C. The total project cost is approximately 12 million PLN, funded partly by the 'Polish Geothermal Water Acquisition' program.

Preparatory work for the Radoszyce GT-1 geothermal exploration well has started in Radoszyce, Poland. The well is designed to reach 1360 meters depth, targeting the Lower Triassic aquifer with an anticipated geothermal water temperature of 40-45°C and a flow rate of around 30 cubic meters per hour.
It is estimated that 0.8 MW of geothermal energy can be extracted. The total project cost is about 12 million PLN, with 9.8 million PLN from the 'Polish Geothermal Water Acquisition' program. Drilling is conducted by UOS Drilling SA, with consulting from PROINSOL Spółka z o.o. sp.k.