PGCIL Secures INR 1,800 Crore for Transmission Upgrade Projects in Tamil Nadu
Power Grid Corporation of India (PGCIL) has been awarded two significant transmission upgrade projects in Tamil Nadu under the regulated tariff mechanism (RTM) framework, with a total estimated cost of over INR 1,800 crore. The first project upgrades the 400kV Udumalpet-Madurai line from a single-circuit to a double-circuit (quad) line for INR 643 crore, addressing the line's surge impedance loading limit and enhancing capacity for renewable energy generation.
This project is projected to complete in more than 2 years. The second project involves reconductoring two 400kV double-circuit lines (Tirunelveli-Udumalpet and Pugalur-Madurai) with HTLS conductor, supporting a capacity of 2,100MVA, with a budget of INR 1,193.5 crore and a completion timeline of 2 years.