Trust Group Installs 1,500m HV Cable for Branston Locks Industrial Park
Trust Group was contracted to install a 1,500m dual circuit 11kV ducted cable system for GTC at Branston Locks. The project involved linking a local distribution network operator substation to the new site, with Trust acting as the principal contractor. The installation included stakeholder coordination and traffic management, utilizing trenchless techniques to minimize disruption, especially while crossing the busy A38. The project was completed successfully, enhancing energy supply for future local economic development.

Trust Group installed a 1,500m dual circuit 11kV ducted cable system at Branston Locks for GTC, connecting a local distribution network operator substation to a new industrial park. Acting as the principal contractor, Trust managed the installation, including stakeholder coordination and traffic management.
The project faced challenges such as running the cable beneath the A38, requiring detailed planning and horizontal directional drilling. The use of trenchless techniques minimized disruption to traffic and the environment. The project was completed successfully, providing a critical high-voltage connection to support local economic growth.




Comments